Prabowo Prioritizes Work on 137 Sumatra Rivers to Prevent Further Flooding
Indonesian President Prabowo Subianto has made river normalization a priority in disaster-hit Aceh, North Sumatra and West Sumatra, where heavy sediment buildup threatens renewed flooding. The work covers 137 rivers, Home Affairs Minister Tito Karnavian said after a limited cabinet meeting at the Presidential Palace in Jakarta on November 9, 2026.

Flood risk amid unfinished recovery
Tito said sediment buildup can cause rivers to overflow their embankments even after light rain. Although the government's rehabilitation and reconstruction program for the three provinces is planned over three years, Prabowo emphasized that river normalization must take priority.
Tito chairs the Task Force for Accelerated Rehabilitation and Reconstruction (Satgas PRR) for post-disaster Sumatra. In its November 9 briefing, the task force said recovery remained incomplete in 10 regencies across the three provinces. Subsequent floods had struck at least 13 regencies and cities, damaging infrastructure that had already been repaired.
Progress varies across the three provinces
Aceh accounts for 31 of the rivers targeted for normalization. As of November 9, work was complete on 15, underway on six and had not begun on 10, according to Tito.
North Sumatra has 48 rivers in the program: work was complete on 28, underway on six and not yet started on 14. In West Sumatra, which has 58 targeted rivers, 12 were complete, 31 were being worked on and 15 were awaiting work.
The government is also targeting 38 river mouths across the three provinces. Tito said seven had been completed, 11 were being worked on and 20 had yet to be started.
Sediment removal, dams and local authority
The Indonesian military (TNI) had cleared an eight-kilometer stretch of river channel in Aceh Tamiang by November 9, according to the task force briefing. Prabowo will also assign the TNI and the Indonesian National Police (Polri) to remove sediment and build embankments along both banks of the rivers.
Separately, the Ministry of Public Works plans to build 106 sabo dams to hold back sediment across the three provinces. Only six had been built as of November 9, the task force reported.
Tito said Energy and Mineral Resources Minister Bahlil Lahadalia is to issue a letter delegating authority for cooperation on the use of sand and stone from the rivers to the regency and city level. River normalization must remain the primary purpose of those arrangements, and the proceeds must go into locally generated revenue, known as PAD.